Project Progress- Waterfall Residencies

Legends Tower C Tower B Tower A
Structure Completed Completed Completed
Blockwork Completed Completed Completed
Gypsum Completed Completed Completed
IPS Flooring Completed Completed Completed
"Flat Tiling (Toilet & Kitchen)" "26th Floor Completed, 27th Floor in Progress" "21st Floor Completed , 22nd Floor in Progress" ""18th Floor completed, 19th Floor in Progress"
SS Railing (Except Glass Fixing) "26th Floor Completed 27th Floor in Progress" "25th Floor Completed 26th Floor in Progress" "22nd Floor Completed 23rd Floor in Progress"
Plumbing Services "31st Floor Completed, 32nd Floor in Progress" "26th Floor Completed, 27th Floor in progress" Completed
Conduiting & AC Drain Services Completed Completed Completed
HVAC Services "32nd Floor Completed, 33rd Floor in Progress" "25th Floor Completed 26th Floor in Progress" "22nd Floor Completed 23rd Floor in Progress"

Basement

Legends Basement
VDF Flooring 95%
Wall Paint 87%
Ceiling Paint 87%
Ventilation Ducting 83%

Club

Refreshment Area 95%
Children Play Area 74%
Banquet and GF kitchen area 56%
GYM Area 77%
Yoga Area 82%
Male SPA Area & Saloon area 78%
Female SPA and corridor Area. 81%
Entrance Lobby 44%
Lift Lobby 42%
Public Toilet (GF) 73%
Restaurent & Bar Area (1st Floor) 78%