| Legends |
Tower C |
Tower B |
Tower A |
| Structure |
Completed |
Completed |
Completed |
| Blockwork |
Completed |
Completed |
Completed |
| Gypsum
|
Completed |
Completed |
Completed |
| IPS Flooring |
Completed |
Completed |
Completed |
| "Flat Tiling
(Toilet & Kitchen)" |
"26th Floor Completed,
27th Floor in Progress" |
"21st Floor Completed ,
22nd Floor in Progress" |
""18th Floor completed,
19th Floor in Progress" |
| SS Railing
(Except Glass Fixing) |
"26th Floor Completed
27th Floor in Progress"
|
"25th Floor Completed
26th Floor in Progress"
|
"22nd Floor Completed
23rd Floor in Progress"
|
| Plumbing Services |
"31st Floor Completed,
32nd Floor in Progress"
|
"26th Floor Completed,
27th Floor in progress"
|
Completed
|
| Conduiting & AC Drain Services
|
Completed |
Completed |
Completed |
| HVAC Services |
"32nd Floor Completed,
33rd Floor in Progress"
|
"25th Floor Completed
26th Floor in Progress"
|
"22nd Floor Completed
23rd Floor in Progress"
|