Tower-A

  • Structure – Superstructure completed.
  • Block Work – 23rd -24th Floor in progress
  • Conduiting – 22nd -23rd Floor in progress
  • Gypsum – 22nd -23rd Floor in progress
  • Balcony Tiling : 4th Floor in Progress
  • Toilet Tiling : 9th Floor in Progress
  • IPS Flooring : 8th Floor in Progress

Tower-B

  • Structure – Superstructure completed.
  • Block Work – 24th -25th Floor in progress
  • Conduiting - 15th-16h Floor in progress
  • Gypsum – 12th-13th Floor in progress
  • Balcony Tiling : 4th Floor in Progress
  • Toilet Tiling : 8th Floor in Progress
  • IPS Flooring : 8th Floor in Progress

Tower-C

  • Structure – Superstructure completed.
  • Block Work – 31st-32nd Floor in progress
  • Conduiting - 28th-29th Floor in progress
  • Gypsum – 30th -31st Floor in progress
  • Balcony Tiling : 3rd Floor in Progress
  • Toilet Tiling : 13th Floor in Progress
  • IPS Flooring : 10th Floor in Progress

Club

  • Banquet & Reception : Terrace Slab in Progress
  • Refreshment Area : Wall Stone Cladding & False Ceiling Framing in Progress
  • Convenient Shop : Wall Gypsum is done
  • Children Play Area : Wall Gypsum is done
  • GYM & YOGA Room: Wall Stone Cladding in progress
  • MALE SPA : Panelling frame in progress

Basement

  • VDF for Parking in Progress
  • STP & Water Tank in Progress
  • Pump Room in Progress
  • Ventilation Ducting in Progress
  • Backfilling for landscaping in progress

Boundary Wall

  • Compound wall with around 305 m casted and in progress

Construction Updates

Enquiry Now

For More Information

Enquire Now