Tower-A

  • Structure – Superstructure completed.
  • Block Work – 24th Floor in progress
  • Conduiting – upto 22nd complete.
  • Gypsum – 23rd Floor in progress
  • Balcony Tiling : 4th Floor in Progress
  • Toilet Tiling : 10th Floor in Progress
  • IPS Flooring : 10th Floor in Progress

Tower-B

  • Structure – Superstructure completed.
  • Block Work – 24th -25th Floor in progress
  • Conduiting - 1st-12th & 18th-22nd Floor completed rest in progress.
  • Gypsum –1st-11th & 20th-21st floor complete rest in progress.
  • Balcony Tiling : 4th Floor in Progress
  • Toilet Tiling : 9th – 10th Floor in Progress
  • IPS Flooring : 9th -10th Floor in Progress

Tower-C

  • Structure – Superstructure completed.
  • Block Work – 31st-32nd Floor in progress
  • Conduiting - 28th-29th Floor in progress
  • Gypsum – 30th -31st Floor in progress
  • Balcony Tiling : 3rd Floor in Progress
  • Toilet Tiling : 15th -16th Floor in Progress
  • IPS Flooring : 10th Floor in Progress

Club

  • Banquet & Reception : Terrace Slab in Progress
  • Refreshment Area : Wall Stone Cladding & False Ceiling Framing in Progress
  • Convenient Shop : Wall Gypsum is done
  • Children Play Area : Wall Gypsum is done
  • GYM & YOGA Room: Wall Stone Cladding in progress (90% complete) and ceiling framing in progress.
  • MALE SPA : Panelling frame in progress

Basement

  • VDF for Parking in Progress (50% area has been done in UBL & LBL)
  • STP & Water Tank in Progress
  • Pump Room- handed over to the services team.
  • DG room area work in progress.
  • Electrical room- handed over to the services team.
  • Ventilation Ducting in Progress
  • Backfilling for landscaping in progress

Boundary Wall

  • Compound wall with around 402 mtr. casted rest in progress.

EWS Area

  • Structure completed upto 3rd floor level.
  • Structure work- 4th floor 70% completed rest and terrace level work in progress.
  • Block work in progress at 1st floor.