Tower-A

  • Structure – 24th Floor & Terrace WIP and Unit-A5 24th Floor in progress.
  • Block Work - 18th-21st Floor in progress
  • Conduiting - 19th-21st Floor in progress
  • Gypsum - 13th-14th Floor in progress
  • Balcony Tiling : 2nd Floor in Progress
  • Toilet Tiling : 5th Floor in Progress
  • IPS Flooring : 2nd Floor in Progress

Tower-B

  • Structure – 27th Floor & Terrace WIP and Unit-B5 24th Floor in progress.
  • Block Work – 21st -22nd Floor in progress
  • Conduiting - 10th Floor in progress
  • Gypsum – 8th-9th Floor in progress
  • Balcony Tiling : 2nd Floor in Progress
  • Toilet Tiling : 5th Floor in Progress
  • IPS Flooring : 2nd Floor in Progress

Tower-C

  • Structure – 34th & Terrace Floor in progress
  • Block Work – 27th -29th Floor in progress
  • Conduiting - 25th-26th Floor in progress
  • Gypsum – 20th -21st Floor in progress
  • Balcony Tiling : 3rd Floor in Progress
  • Toilet Tiling : 6th Floor in Progress
  • IPS Flooring : 3rd Floor in Progress

Club

  • Banquet & Reception : Terrace Slab in Progress
  • Refreshment Area : Wall Stone Cladding & False Ceiling Framing in Progress
  • Convenient Shop : Wall Gypsum is done
  • Children Play Area : Wall Gypsum is done
  • GYM & YOGA Room: Wall Gypsum in progress
  • MALE SPA : Blockwork Partition in progress

Basement

  • VDF for Parking in Progress
  • STP & Water Tank in Progress
  • Pump Room in Progress
  • Backfilling for landscaping in progress

Boundary Wall

  • Compound wall with around 80 m casted and in progress