Legends |
Tower C |
Tower B |
Tower A |
Structure |
Completed |
Completed |
Completed |
Blockwork |
"33rd Floor Completed,
34th Floor in Progress"
|
"26th Floor Completed,
27th Floor in progress"
|
Completed
|
Gypsum
|
"32nd Floor Completed ,
33rd Floor in Progress"
|
"23rd Floor Completed
24th Floor in Progress"
|
"22nd Floor Completed,
23rd Floor in Progress"
|
IPS Flooring |
"20th Floor Completed,
21st Floor in Progress"
|
"12th Floor Completed,
13th Floor in Progress"
|
"17th Floor Completed,
18th Floor in Progress"
|
Flat Tiling |
"Upto 17th Floor All Toilet & Kitchen Completed,
18th in Progress"
|
"Upto 10th Floor Completed in Toilets,
11th Floor in Progress"
|
"All Toilet & Kitchen upto 10th Floor completed,
11th Floor in Progress"
|
SS Railing
(Except Glass Fixing) |
"8th Floor Completed
9th Floor in Progress"
|
"20th Floor Completed
21st Floor in Progress"
|
"17th Floor Completed
18th Floor in Progress"
|
Plumbing Services |
"26th Floor Completed,
27th Floor in Progress"
|
"22nd Floor Completed,
23rd Floor in progress"
|
"22nd Floor Completed,
23rd Floor in progress"
|
Conduiting & AC Drain Services |
"32nd Floor Completed,
33rd Floor in Progress"
|
"24th Floor Completed,
25th Floor in Progress"
|
"22nd Floor completed,
23rd Floor in Progress"
|
HVAC Services |
"21st Floor Completed,
22nd Floor in Progress"
|
"22nd Floor Completed
23rd Floor in Progress"
|
"22nd Floor Completed
23rd Floor in Progress"
|