Project Progress- Waterfall Residencies

Legends Tower C Tower B Tower A
Structure Completed Completed Completed
Blockwork "33rd Floor Completed, 34th Floor in Progress" "26th Floor Completed, 27th Floor in progress" Completed
Gypsum "32nd Floor Completed , 33rd Floor in Progress" "23rd Floor Completed 24th Floor in Progress" "22nd Floor Completed, 23rd Floor in Progress"
IPS Flooring "20th Floor Completed, 21st Floor in Progress" "12th Floor Completed, 13th Floor in Progress" "17th Floor Completed, 18th Floor in Progress"
Flat Tiling "Upto 17th Floor All Toilet & Kitchen Completed, 18th in Progress" "Upto 10th Floor Completed in Toilets, 11th Floor in Progress" "All Toilet & Kitchen upto 10th Floor completed, 11th Floor in Progress"
SS Railing (Except Glass Fixing) "8th Floor Completed 9th Floor in Progress" "20th Floor Completed 21st Floor in Progress" "17th Floor Completed 18th Floor in Progress"
Plumbing Services "26th Floor Completed, 27th Floor in Progress" "22nd Floor Completed, 23rd Floor in progress" "22nd Floor Completed, 23rd Floor in progress"
Conduiting & AC Drain Services "32nd Floor Completed, 33rd Floor in Progress" "24th Floor Completed, 25th Floor in Progress" "22nd Floor completed, 23rd Floor in Progress"
HVAC Services "21st Floor Completed, 22nd Floor in Progress" "22nd Floor Completed 23rd Floor in Progress" "22nd Floor Completed 23rd Floor in Progress"

Basement

Legends Basement
VDF Flooring 82%
Wall Paint 72%
Ceiling Paint 72%
Ventilation Ducting 65%

Club

Refreshment Area 90%
Children Play Area 60%
Banquet and GF kitchen area 50%
GYM Area 70%
Yoga Area 75%
Male SPA Area & Saloon area 70%
Female SPA and corridor Area. 75%
Entrance Lobby 35%
Lift Lobby 25%
Public Toilet (GF) 65%
Restaurent & Bar Area (1st Floor) 40%