Project Progress- Waterfall Residencies

Legends Tower C Tower B Tower A
Structure Completed Completed Completed
Blockwork Completed Completed Completed
Gypsum Completed Completed Completed
IPS Flooring "25th Floor Completed, 26th Floor in Progress" Completed Completed
"Flat Tiling (Toilet & Kitchen)" ""21st Floor Completed, 22nd Floor in Progress" ""13th Floor Completed , 14th Floor in Progress" "13th Floor completed, 14th Floor in Progress"
SS Railing (Except Glass Fixing) "20th Floor Completed 21st Floor in Progress" "23rd Floor Completed 24th Floor in Progress" "20th Floor Completed 21st Floor in Progress"
Plumbing Services "31st Floor Completed, 32nd Floor in Progress" "26th Floor Completed, 27th Floor in progress" "23rd Floor Completed, 24th Floor in progress"
Conduiting & AC Drain Services Completed Completed Completed
HVAC Services "30th Floor Completed, 31st Floor in Progress" "25th Floor Completed 26th Floor in Progress" "22nd Floor Completed 23rd Floor in Progress"

Basement

Legends Basement
VDF Flooring 92%
Wall Paint 83%
Ceiling Paint 83%
Ventilation Ducting 78%

Club

Refreshment Area 95%
Children Play Area 71%
Banquet and GF kitchen area 55%
GYM Area 76%
Yoga Area 81%
Male SPA Area & Saloon area 77%
Female SPA and corridor Area. 81%
Entrance Lobby 41%
Lift Lobby 35%
Public Toilet (GF) 71%
Restaurent & Bar Area (1st Floor) 47%