| Legends |
Tower C |
Tower B |
Tower A |
| Structure |
Completed |
Completed |
Completed |
| Blockwork |
Completed |
Completed |
Completed |
| Gypsum
|
Completed |
Completed |
Completed |
| IPS Flooring |
"25th Floor Completed,
26th Floor in Progress"
|
Completed |
Completed |
| "Flat Tiling
(Toilet & Kitchen)" |
""21st Floor Completed,
22nd Floor in Progress"
|
""13th Floor Completed ,
14th Floor in Progress"
|
"13th Floor completed,
14th Floor in Progress"
|
| SS Railing
(Except Glass Fixing) |
"20th Floor Completed
21st Floor in Progress"
|
"23rd Floor Completed
24th Floor in Progress"
|
"20th Floor Completed
21st Floor in Progress"
|
| Plumbing Services |
"31st Floor Completed,
32nd Floor in Progress"
|
"26th Floor Completed,
27th Floor in progress"
|
"23rd Floor Completed,
24th Floor in progress"
|
| Conduiting & AC Drain Services
|
Completed |
Completed |
Completed |
| HVAC Services |
"30th Floor Completed,
31st Floor in Progress"
|
"25th Floor Completed
26th Floor in Progress"
|
"22nd Floor Completed
23rd Floor in Progress"
|