Project Progress- Waterfall Residencies

Legends Tower C Tower B Tower A
Structure Completed Completed Completed
Blockwork Completed Completed Completed
Gypsum Completed Completed Completed
IPS Flooring "29th Floor Completed, 30th Floor in Progress" Completed Completed
"Flat Tiling (Toilet & Kitchen)" "24th Floor Completed, 25th Floor in Progress" "18th Floor Completed , 19th Floor in Progress" "15th Floor completed, 16th Floor in Progress"
SS Railing (Except Glass Fixing) "22nd Floor Completed 23rd Floor in Progress" "24th Floor Completed 25th Floor in Progress" "22nd Floor Completed 23rd Floor in Progress"
Plumbing Services "31st Floor Completed, 32nd Floor in Progress" "26th Floor Completed, 27th Floor in progress" Completed
Conduiting & AC Drain Services Completed Completed Completed
HVAC Services "31st Floor Completed, 32nd Floor in Progress" "25th Floor Completed 26th Floor in Progress" "22nd Floor Completed 23rd Floor in Progress"

Basement

Legends Basement
VDF Flooring 93%
Wall Paint 85%
Ceiling Paint 85%
Ventilation Ducting 80%

Club

Refreshment Area 95%
Children Play Area 72%
Banquet and GF kitchen area 56%
GYM Area 76%
Yoga Area 81%
Male SPA Area & Saloon area 77%
Female SPA and corridor Area. 81%
Entrance Lobby 42%
Lift Lobby 37%
Public Toilet (GF) 72%
Restaurent & Bar Area (1st Floor) 48%