Tower-A

  • Structure – Terrace Floor in progress.
  • Block Work – 22nd -24th Floor in progress
  • Conduiting – 22nd -23rd Floor in progress
  • Gypsum - 17th-18th Floor in progress
  • Balcony Tiling : 4th Floor in Progress
  • Toilet Tiling : 5th Floor in Progress
  • IPS Flooring : 5th Floor in Progress

Tower-B

  • Structure – Terrace WIP and Unit-B5 25th Floor in progress.
  • Block Work – 21st -22nd Floor in progress
  • Conduiting - 13th-14th Floor in progress
  • Gypsum – 11th-12th Floor in progress
  • Balcony Tiling : 4th Floor in Progress
  • Toilet Tiling : 5th Floor in Progress
  • IPS Flooring : 4th Floor in Progress

Tower-C

  • Structure – 34th & Terrace Floor in progress
  • Block Work – 29th -30th Floor in progress
  • Conduiting - 26th-27th Floor in progress
  • Gypsum – 25th -26th Floor in progress
  • Balcony Tiling : 3rd Floor in Progress
  • Toilet Tiling : 8th Floor in Progress
  • IPS Flooring : 4th Floor in Progress

Club

  • Banquet & Reception : Terrace Slab in Progress
  • Refreshment Area : Wall Stone Cladding & False Ceiling Framing in Progress
  • Convenient Shop : Wall Gypsum is done
  • Children Play Area : Wall Gypsum is done
  • GYM & YOGA Room: Wall Gypsum in progress
  • MALE SPA : Blockwork Partition in progress

Basement

  • VDF for Parking in Progress
  • STP & Water Tank in Progress
  • Pump Room in Progress
  • Backfilling for landscaping in progress

Boundary Wall

  • Compound wall with around 150 m casted and in progress