Project Progress- Waterfall Residencies

Legends Tower C Tower B Tower A
Structure Completed Completed Completed
Blockwork 32nd Floor Completed, 33rd Floor in Progress 25th Floor Completed, 26th Floor in progress 22nd Floor Completed, 23rd Floor in Progress
Gypsum 30th Floor Completed , 31st Floor in Progress 14th Floor Completed, 19th to 22nd Floor Completed. 23rd Floor in Progress 22nd Floor Completed, 23rd Floor in Progress
IPS Flooring 9th Floor Completed, 10th Floor in Progresss 9th Floor Completed, 10th & Floor in Progresss 8th Floor Completed, 9th Floor in Progress
Flat Tiling Upto 17th Floor All Toilet & Kitchen Completed, 18th in Progress Upto 10th Floor Completed in Toilets, 11th Floor in Progress All Toilet & Kitchen upto 10th Floor completed, 11th Floor in Progress
SS Railing (Except Glass Fixing) 3rd Floor Completed 4th Floor in Progress 17th Floor Completed 18th Floor in Progress 17th Floor Completed 18th Floor in Progress
Plumbing Services 23rd Floor Completed, 24th Floor in Progress 18th Floor Completed, 19th Floor in progress 17th Floor Completed, 18th Floor in progress
Conduiting & AC Drain Services 32nd Floor Completed, 33rd Floor in Progress 14th Floor Completed, 18th to 21st Floor Completed, 15th Floor in Progress 22nd Floor in Progress 22nd Floor completed, 23rd Floor in Progress
HVAC Services 17th Floor Completed, 18th in Progress 16th Floor Completed 17th Floor in Progress 13th Floor Completed 14th Floor in Progress

Basement

Legends Basement
VDF Flooring 65%
Wall Paint 70%
Ceiling Paint 70%
Ventilation Ducting 50%

Club

Refreshment Area 85%
Children Play Area 50%
Banquet and GF kitchen area 40%
GYM Area 65%
Yoga Area 65%
Male SPA Area & Saloon area 60%
Female SPA and corridor Area. 55%
Entrance Lobby 25%
Lift Lobby 20%
Public Toilet (GF) 45%
Restaurent & Bar Area (1st Floor) 30%

Construction Updates