Legends |
Tower C |
Tower B |
Tower A |
Structure |
Completed |
Completed |
Completed |
Blockwork |
32nd Floor Completed,
33rd Floor in Progress
|
25th Floor Completed,
26th Floor in progress
|
22nd Floor Completed,
23rd Floor in Progress
|
Gypsum
|
30th Floor Completed ,
31st Floor in Progress
|
14th Floor Completed,
19th to 22nd Floor Completed.
23rd Floor in Progress
|
22nd Floor Completed,
23rd Floor in Progress
|
IPS Flooring |
9th Floor Completed,
10th Floor in Progresss |
9th Floor Completed,
10th & Floor in Progresss |
8th Floor Completed,
9th Floor in Progress |
Flat Tiling |
Upto 17th Floor All Toilet & Kitchen Completed,
18th in Progress |
Upto 10th Floor Completed in Toilets,
11th Floor in Progress |
All Toilet & Kitchen upto 10th Floor completed,
11th Floor in Progress |
SS Railing
(Except Glass Fixing) |
3rd Floor Completed
4th Floor in Progress |
17th Floor Completed
18th Floor in Progress |
17th Floor Completed
18th Floor in Progress |
Plumbing Services |
23rd Floor Completed,
24th Floor in Progress |
18th Floor Completed,
19th Floor in progress |
17th Floor Completed,
18th Floor in progress |
Conduiting & AC Drain Services |
32nd Floor Completed,
33rd Floor in Progress |
14th Floor Completed,
18th to 21st Floor Completed,
15th Floor in Progress
22nd Floor in Progress |
22nd Floor completed,
23rd Floor in Progress |
HVAC Services |
17th Floor Completed,
18th in Progress |
16th Floor Completed
17th Floor in Progress |
13th Floor Completed
14th Floor in Progress |