Project Progress- Waterfall Residencies

Legends Tower C Tower B Tower A
Structure Completed Completed Completed
Blockwork "33rd Floor Completed, 34th Floor in Progress" "26th Floor Completed, 27th Floor in progress" Completed
Gypsum "32nd Floor Completed , 33rd Floor in Progress" "15th Floor Completed, 16th Floor in Progress 17th to 22nd Floor Completed. 23rd Floor in Progress" "22nd Floor Completed, 23rd Floor in Progress"
IPS Flooring "13th Floor Completed, 14th Floor in Progresss" "10th Floor Completed, 11th & Floor in Progresss" "13th Floor Completed, 14th Floor in Progress"
Flat Tiling "Upto 17th Floor All Toilet & Kitchen Completed, 18th in Progress" "Upto 10th Floor Completed in Toilets, 11th Floor in Progress" "All Toilet & Kitchen upto 10th Floor completed, 11th Floor in Progress"
SS Railing (Except Glass Fixing) "6th Floor Completed 7th Floor in Progress" "17th Floor Completed 18th Floor in Progress" "17th Floor Completed 18th Floor in Progress"
Plumbing Services "23rd Floor Completed, 24th Floor in Progress" "18th Floor Completed, 19th Floor in progress" "18th Floor Completed, 19th Floor in progress"
Conduiting & AC Drain Services "32nd Floor Completed, 33rd Floor in Progress" "23rd Floor Completed, 24th Floor in Progress" "22nd Floor completed, 23rd Floor in Progress"
HVAC Services "20th Floor Completed, 21st in Progress" "18th Floor Completed 19th Floor in Progress" "21st Floor Completed 22nd Floor in Progress"

Basement

Legends Basement
VDF Flooring 75%
Wall Paint 70%
Ceiling Paint 70%
Ventilation Ducting 60%

Club

Refreshment Area 85%
Children Play Area 50%
Banquet and GF kitchen area 40%
GYM Area 70%
Yoga Area 75%
Male SPA Area & Saloon area 70%
Female SPA and corridor Area. 65%
Entrance Lobby 30%
Lift Lobby 20%
Public Toilet (GF) 50%
Restaurent & Bar Area (1st Floor) 30%