Refreshment Area | Service works : Completed except FTTH & Music system. |
Wall Claddding : Completed Except Sealer Coat. | |
POP False Ceiling : Completed. | |
Stone Flooring : In Progress | |
Children Play Area | Gypsum Plaster : Completed |
False Ceiling : Framing work completed | |
Service works in Ceiling : Completed except FTTH & Music system. | |
Banquet and GF kitchen area | Gypum Plaster : In progess |
Services works : HVAC & Fire in progress. | |
GYM Area | Service works : HVAC, Fire & Electriacl in progress. |
Wall Claddding : 90% completed | |
False Ceiling : Framing Completed for MEP works. | |
Wooden Wall Panelling : in progress | |
Yoga Area | Gypsum Plaster : completed |
Flooring : Tile Flooring completed. | |
Framing for false ceiling : Completed. | |
Male SPA Area & Saloon area | Wall Cladding (Stone) : 80% Completed |
Service Works : in progess i.e. Elec, HVAC, Plumbing etc. | |
False Ceiling : Framing Completed. | |
Wooden Panelling : Base Ply works completed | |
Female SPA and corridor Area. | Wall Cladding (Stone) : 65% Completed |
Service Works : in progess i.e. Elec, HVAC, Plumbing etc. | |
Wooden Panelling : Base Ply works completed. | |
False Ceiling : Framing in progess. | |
Dry Stone Cladding (Corridor) : 80% Completed | |
Entrance Lobby | Services Works : HVAC & Fire works in progess |
Entrance Canopy Club : MS works in progess | |
Lift Lobby | Services Works : in progress |
Wooden Wall Panelling : Base Ply works Completed. | |
Public Toilet (GF) | Flooring : Tile Flooring started. (Tower C). |
Blockwork : Completed for services works. (Tower A). | |
Restaurent & Bar Area (1st Floor) | Blockwork : in progess |
Legends | Tower C | Tower B | Tower A |
---|---|---|---|
Structure | Completed | Completed | Completed |
Blockwork | 31st Floor Completed; 32nd Floor in Progress |
24th Floor Completed; 25th Floor in progress |
22nd Floor Completed; |
Gypsum | 30th Floor Completed ; 31st Floor in Progress |
12th Floor Completed; 20th; 21st & 22nd Floor Completed. 13th & 22nd Floor in Progress |
22nd Floor Completed; 23rd Floor in Progress |
IPS Flooring | 9th Floor Completed; 10th Floor in Progresss |
9th Floor Completed; 10th & Floor in Progresss |
8th Floor Completed; 9th Floor in Progress |
Flat Tiling | Upto 17th Floor All Toilet & Kitchen Completed; 18th in Progress |
Upto 10th Floor Completed in Toilets; 11th Floor in Progress |
All Toilet & Kitchen upto 9th Floor completed; 11th Floor in Progress |
SS Railing (Except Glass Fixing) |
1st Floor in Progress | 15th Floor Completed 16th Floor in Progress |
15th Floor Completed 16th Floor in Progress |
Plumbing Services | 22nd Floor Completed; 23rd Floor in Progress |
17th Floor Completed; 18th Floor in progress |
17th Floor Completed; 18th Floor in progress |
Conduiting & AC Drain Services | 31st Floor Completed; 32nd Floor in Progress |
14th Floor Completed; 18th to 21st Floor Completed; 15th Floor in Progress 22nd Floor in Progress |
22nd Floor completed; 23rd Floor in Progress |
HVAC Services | 17th Floor Completed; 18th in Progress |
16th Floor Completed 17th Floor in Progress |
13th Floor Completed 14th Floor in Progress |