Project Progress- Waterfall Residencies

Legends Tower C Tower B Tower A
Structure Completed Completed Completed
Blockwork Completed Completed Completed
Gypsum Completed Completed Completed
IPS Flooring "33rd Floor Completed, 34th Floor in Progress" Completed Completed
"Flat Tiling (Toilet & Kitchen)" "25th Floor Completed, 26th Floor in Progress" "20th Floor Completed , 21st Floor in Progress" ""17th Floor completed, 18th Floor in Progress"
SS Railing (Except Glass Fixing) "23rd Floor Completed 24th Floor in Progress" "25th Floor Completed 26th Floor in Progress" "22nd Floor Completed 23rd Floor in Progress"
Plumbing Services "31st Floor Completed, 32nd Floor in Progress" "26th Floor Completed, 27th Floor in progress" Completed
Conduiting & AC Drain Services Completed Completed Completed
HVAC Services "32nd Floor Completed, 33rd Floor in Progress" "25th Floor Completed 26th Floor in Progress" "22nd Floor Completed 23rd Floor in Progress"

Basement

Legends Basement
VDF Flooring 94%
Wall Paint 86%
Ceiling Paint 86%
Ventilation Ducting 82%

Club

Refreshment Area 95%
Children Play Area 73%
Banquet and GF kitchen area 56%
GYM Area 76%
Yoga Area 82%
Male SPA Area & Saloon area 77%
Female SPA and corridor Area. 81%
Entrance Lobby 43%
Lift Lobby 40%
Public Toilet (GF) 73%
Restaurent & Bar Area (1st Floor) 48%